Auditors put MPs on the spot over stalled projects

Many newly elected legislators are increasingly abandoning projects initiated by their predecessors in favor of launching fresh ones. This growing trend has led to numerous stalled initiatives costing taxpayers millions of shillings, thereby depriving citizens of the intended benefits that completed projects would have delivered. As a result, the anticipated value for money invested in these developments remains unrealized. The abandoned projects further highlight persistent concerns of inefficiency, financial mismanagement, wastage of public resources, and the absence of accountability in public spending.

Fiscal year
According to the Auditor-General’s report for the fiscal year 2023/24, which ended on June 1, 2024, projects worth Kshs. 495,613,717 were reported as stalled or abandoned across 29 National Government Constituencies Development Funds (NGCDF). Auditor-General Nancy Gathungu revealed that in Matayos NGCDF, stalled projects were valued at Kshs. 85,217,471, while Bomachoge Borabu NGCDF recorded abandoned primary school projects worth Kshs. 73,079,495. In Ainabkoi, eight projects amounting to Kshs. 15,532,783 had stalled. Similarly, in Awendo, Kshs. 13,500,000 was allocated for the construction of eight classrooms, but the project remains incomplete.

In Bobasi, the construction of a laboratory, library, and classrooms at St. Mathews Chitago Secondary School — which began in the 2018/2019 financial year at a cost of Kshs. 3,700,000 — has dragged on without completion. Bondo NGCDF reported a stalled school project valued at Kshs. 9,000,000. In Butere, the contract for an administration block at Bulanda RC Primary School was awarded for Kshs. 3,330,486, with 69 percent (Kshs. 2,300,042) already paid. Yet verification revealed the contractor had deserted the site, leaving floors uncured, windows uninstalled, and walls unplastered.

Nancy Gathungu, Auditor-General
PHOTO | COURTESY | TRBN |

For the happiest life, days should be rigorously planned, nights left open to chance pennews wordpress theme

Allocation
Funyula NGCDF allocated Kshs. 4,000,000 for a dormitory to host 256 students starting September 2, 2024, but only partial excavation of the substructure had been done. Likewise, a Kshs. 7,000,000 allocation for an eight-classroom tuition block saw incomplete walling, roofing, fittings, and electrical work, bringing the value of stalled projects to Kshs. 11,000,000. In Emgwen, stalled classrooms and an administration block were valued at Kshs. 5,850,000. Garsen NGCDF registered incomplete works worth Kshs. 17,657,173. In Ikolomani, the construction of a storied building and classrooms at Bushiangala Primary School collapsed after consuming Kshs. 5,000,000.

Modern library
Homa Bay Town NGCDF abandoned the construction of a modern library at Ogande Girls High School valued at Kshs. 40,000,000. Kapseret had four projects worth Kshs. 10,606,835 stalled, including a police station at Kesses. Kabuchai NGCDF disbursed Kshs. 10,000,000 for a storied classroom block at Busakala Primary School, but the contractor abandoned the site after the first-floor slab despite a total contract sum of Kshs. 18,950,990. Kigumo’s science laboratory project worth Kshs. 3,890,000 was abandoned. Konoin’s Kshs. 2,000,000 dining hall at Chebangang Secondary School stalled, forcing contract termination. Kitui East’s Kshs. 5,000,000 Assistant County Commissioner’s Office Block was left incomplete after only substructure and roofing works were done, despite full payment to the contractor.

Change your thoughts, you change your world

Norman Vincent

Related posts

Court clears eviction of Kangaita land buyers

thepeople tribune

Wahome enters Murang’a gubernatorial battle

thepeople tribune

We Know What Works—Why Aren’t We Scaling Contraception to Save Mothers?

thepeople tribune

Church defends Ruto record, warns against election violence

thepeople tribune

Discipline, leadership drive Dede Girls revival

thepeople tribune

Inside Kenya’s deputy leadership dynamics

thepeople tribune

Leave a Comment